Wilson & Associates preformed the Engineering and Surveying subcontract and the Erosion and Sediment Control Supervision subcontract on three contiguous sections of improvements to I-75 North of Chattanooga, TN. Field adjustments were continuously kept up to date to make the new construction match existing conditions and all three of the projects finished on-time with no environmental issues.
The project, which included widening the section of I-75 from one mile south of Exit 11 to one mile north of Exit 11 to four lanes in each direction, also included the construction of new interstate bridges over Wolftever Creek and Lee Highway (SR-2/US-11) and major improvements to the interchange at Exit 11.
“To successfully complete a project of this magnitude is always a great accomplishment, but to do it early is even more impressive.” ~ stated then TDOT Region 2 Director Bob Brown.