Work Order No. | 97818-1011 |
---|---|
Requester Name | Justin Wilson |
RequesterEmail | Email hidden; Javascript is required. |
Date Requested | 10/04/2018 |
Date Due | 10/08/2018 |
Priority | High |
Manager | Jonathan Bailey |
Type of Work Order | Data Work Order |
Description of Task | On Phase 3 Saturn Parkway for the project, we are needing slit fence location and ROW locations for staking. If the ROW is in the plans, we can use the station and o/s as long as we have an alignment for the roadways. |
Data Location |
|
Flight Area Information | |
Assigned to | Zachary McCown |
Completed Data Files |
|
Data Path / Address | J:\Geopak Projects\97818\Machine Control\10-5-18 |
Special Notes | Zip file attached to work order containing dxf and pro file as requested. |
WO Files Upload | Work-Order-97818-1011.zip |
Date Started | 2018-10-04 |
Date Completed | 2018-10-08 |